Past exam questions (6)
2023 · Paper 1 · Q5(c) · p.4
Using notes and a freehand sketch, show best practice design detailing that will prevent the formation of a thermal bridge at the abutment of the flat roof and external concrete block wall with a full-fill insulated cavity. [Visual aid: Image: Cross-section of a highly insulated flat roof.]
Marking scheme
Best practice design detailing that will prevent thermal bridge. Notes / discussion (5), Sketch (10).
2022 · Paper 1 · Q1(b) · p.2
On your drawing, indicate the typical design detailing to prevent the formation of a thermal bridge at the junction of the flat roof and the rear wall of the house.
2021 · Paper 1 · Q1(b) · p.2
On your drawing, show the typical design detailing that will prevent the formation of a thermal bridge at the threshold. [Visual aid: Diagram: An external wooden door with vertical sheeting, a 400 mm concrete block wall with insulated cavity, and a solid concrete ground floor with hardwood finish.]
2020 · Paper 1 · Q5(c) · p.4
Using notes and a freehand sketch, show best practice design detailing that will prevent the formation of a thermal bridge at the junction of the concrete floor and an external concrete block wall with a full-fill insulated cavity. [Visual aid: Diagram showing a cross-section of a highly insulated solid concrete ground floor with hardwood finish.]
Marking scheme
[Diagram: Best practice design detailing to prevent thermal bridge. Performance Criteria: Design detail (Notes - 4 marks, Sketch - 8 marks). Total for (c) is 12 marks.]
2015 · Paper 1 · Q9(b) · p.5
Discuss the importance of designing a building envelope that is thermal bridge free. [Visual aid: Diagram showing an outline section through a two-storey house with circled locations]
Marking scheme
Discussion - Thermal bridge free building envelope (12 marks): Discussion (point 1) - 2 marks for point, 4 marks for discussion (6 marks). Discussion (point 2) - 2 marks for point, 4 marks for discussion (6 marks). TOTAL 60 marks.
2015 · Paper 1 · Q9(a) · p.5
Select any three locations from those circled on the drawing and, using notes and freehand sketches, show best practice design detailing that will prevent the formation of a thermal bridge at each location selected. [Visual aid: Diagram showing an outline section through a two-storey house with circled locations]
Marking scheme
Thermal bridging details - Three locations (6 x 8 marks): Location 1: Notes (8 marks), Sketches (8 marks). Location 2: Notes (8 marks), Sketches (8 marks). Location 3: Notes (8 marks), Sketches (8 marks).