Study notes
No notes have been generated for this topic yet. Open the topic page online and click Generate notes first.
Past exam questions (1)
2018 · Paper 1 · Q2(b) · p.2
For each risk discussed at 2(a) above, show, using notes and freehand sketches, two best practice guidelines that should be observed to reduce the possibility of injury to a worker undertaking each task. [Visual aid: Image: Excavation on a construction site showing trench and underground cables.]
Marking scheme
Two best practice guidelines to reduce injury: Excavating for electrical cables: Guideline 1 (3 for note, 3 for sketch) (6 marks); Guideline 2 (3 for note, 3 for sketch) (6 marks). Working in a deep trench: Guideline 1 (3 for note, 3 for sketch) (6 marks); Guideline 2 (3 for note, 3 for sketch) (6 marks). Working at slating a roof: Guideline 1(3 for note, 3 for sketch) (6 marks); Guideline 2(3 for note, 3 for sketch) (6 marks).