2015 · Paper 1 · Q1(a) · p.2
To a scale of 1:10, draw a vertical section through the centre of the door. Show the typical construction details from 500 mm below finished floor, through the floor, the threshold, the external wall, the door and doorframe to a level 300 mm above the top of the door frame. [Visual aid: Diagram of a house entrance with door and wall details]
Marking scheme
Main entrance and door: Any 11 points x 4 marks (Drawing 3, Annotation 1) - Blockwork - deadwork (4 marks), Hardcore with sand blinding (4 marks), Radon barrier/DPM (4 marks), Floor insulation (4 marks), Subfloor and tile (4 marks), Drainage channel (4 marks), Level surface to drainage channel (4 marks), High performance door – insulated (standard door 2 marks) (4 marks), Doorframe - thermally broken and seals (standard frame 2 marks) (4 marks), Lintels (4 marks), Stepped DPC at head (4 marks), Racking sheeting and strap (4 marks), Breather membrane (4 marks), Timber studs (4 marks), Vapour diffusion cavity 50 – 100 mm (4 marks), Concrete block external leaf and render (4 marks), Fireproof cavity closer (4 marks), Internal vapour barrier/taping - airtightness membrane (4 marks), Service cavity (4 marks), Plaster slab and skimcoat (4 marks). Draughting (4 marks) Scale (4 marks) (Excellent 4, Good 3, Fair 2) (8 marks). (b) Ease of access sloped threshold and upstand (8 marks). TOTAL 60 marks.
2015 · Paper 1 · Q5(c) · p.3
Using notes and freehand sketches, show best practice design detailing to prevent the ingress of water at the window head in the wall of the new house specified at 5(a) above. [Visual aid: Diagram showing a cross-section of an external wall with insulation]
Marking scheme
Prevent ingress of water at window head (2 x 5 marks): Notes / annotations (5 marks), Sketches (5 marks). TOTAL 60 marks.